Managing Microsoft Dynamics Implementations
Question No: 11
Which document is used in the Microsoft Dynamics Sure Step Methodology to document project risks?
-
risk category
-
risk register
-
risk response strategies
-
risk analysis
Answer: B
Question No: 12
What is the maximum time allocated to a developer task within a sprint cycle?
-
8 hours
-
16 hours
-
1 day
-
30 days
Answer: B
Explanation: http://blogs.msdn.com/b/visualstudioalm/archive/2014/03/03/sample-chapter- scrum-agile-practices-and-visual-studio-from-the-book-adopting-agile-software-practices- from-backlog-to-continuous-feedback-edition-3.aspx#_top
The development phase in agile execution operates according to a Scrum development model. The life cycle is divided to 30-days sprint cycles and daily sprint cycle contains analysis, design, coding implementation and end up with solution test, and finalizing product specification.
Here is how it goes;
->Solution Backlog: where the solution feature list is listed
->Release Backlog: where identify and prioritize set of features to be developed during 30 day sprint, and identify each feature time estimation (story point),
->Sprint Backlog: is the breakdown of release backlog according to feature priority and estimation it could be 3-days to one month (daily sprint)
->User story: where descript feature business function, users (roles), and test script (less documentation)
->Defect Backlog: where identify and reporting system bugs
->Standup daily meeting: what we did (status), and what we have today
http://social.technet.microsoft.com/wiki/cfs-filesystemfile.ashx/ key/communityserver- wikis-components-files/00-00-00-00-05/3022.Sure-Step-Agile-Implementation.jpg
clip_image005
http://social.technet.microsoft.com/wiki/contents/articles/5768.microsoft-dynamics-sure- step-agile-implementation.aspx
Question No: 13
You need to create a project by using the Sure Step Project Creation Wizard.
Which two properties must you identify in order to proceed? (Each correct answer presents part of the solution. Choose two.)
-
engagement type
-
product
-
project implementation phase
-
product version
Answer: A,B
Explanation: 1. In the Microsoft Dynamics Sure Step main window, click the Projects tab.
-
Click Project List, and then click Create New Project.
-
On the Sure Step Project Creation Wizard welcome page, click Next.
-
On the “Add new project data” window, choose a Solution, Product, and Engagement Type. Type your project name and optionally fill in the rest of the fields. Click Next to continue.
Etc.
http://blogs.msdn.com/b/ukax/archive/2012/01/10/sure-step-online-project-wizard.aspx
Question No: 14
You are a project manager for a technology consulting company.
Your team is finalizing a commercial engagement proposal for presentation and sign-off. In conjunction with the engagement manager, you need to provide details for the proposal.
Which two details should you provide? (Each correct answer presents part of the solution. Choose two.)
-
functional details
-
project scope details
-
technical details
-
the licensing and service contract agreements
-
the statement of work
-
Answer: D,E
Explanation: http://technet.microsoft.com/en-us/aa699451.aspx
Question No: 15
You are a project manager. You use the classic triple constraint model. If one constraint is changed, what happens to the other constraints?
-
The project#39;s quality constraint will change.
-
The project#39;s expectations constraint will change.
-
At least one of the other constraints must also change.
-
The customer#39;s benefits constraint will change.
Answer: C
Reference:http://www.tonyadamspm.com/2012/07/quality-challenging-the-pm-triple- constraint/
Question No: 16
You are preparing for a go live cutover.
You need to create the go live cutover document. Which items should you add to the document?
-
the operational and support activities for production operations
-
the detailed process steps to be included in the cutover
-
the details of the production environment and disaster recovery information
-
a high-level overview of cutover activities and those involved
Answer: B
Explanation: Chapter 8 – Planning Phase: Creating the Project Plans http://technet.microsoft.com/en-us/library/bb497050.aspx
Question No: 17
You are a project manager.
You create a work breakdown structure (WBS).
What is the next step when you use the Microsoft Dynamics Sure Step Methodology resource management techniques?
-
Plan material resources that will be needed.
-
Plan and use the plan-do-check-act cycle.
-
Plan and collect the project requirements.
-
Plan and schedule stakeholder project reviews.
Answer: A
Explanation: http://technet.microsoft.com/en-us/library/hh227544.aspx
Question No: 18
You are a project manager. You are running a project by using the waterfall delivery method. The project is in the development phase. Which Microsoft Dynamics Sure Step Methodology supplemental documents are created to support the training?
-
performance test documents
-
data migration documents
-
user test documents
-
user guides
Answer: D
Explanation: http://en.wikipedia.org/wiki/Waterfall_model http://blogs.msdn.com/b/dpe_nigeria/archive/2012/06/13/new-tfs-template-available-quot- agile-dev-in-a-waterfall-environment-quot-govdev.aspx
Question No: 19
You are explaining Sure Step’s approach to project management to a colleague. Which definition should you use?
-
Project management is an approach to guide the development of project scope.
-
Project management is an approach to plan project scheduling at the beginning of the project.
-
Project management is an approach to plan and guide project processes from start to finish.
-
Project management is an approach to monitor and measure project progress to identify variances from the plan.
Answer: C
Explanation: http://technet.microsoft.com/en-us/library/aa496439.aspx
Operations Review Team Role Matrix http://technet.microsoft.com/en-us/library/cc526647.aspx Deliver Phase Overview
http://technet.microsoft.com/en-us/library/cc543223.aspx
envisioning phase
http://technet.microsoft.com/en-us/library/bb497039.aspx
Question No: 20
You are a project manager, and you use Microsoft Dynamics Sure Step for implementations of Microsoft Dynamics products for your customers.
Your customer#39;s major stakeholders identify significant changes that will increase the scope of a project.
Which two risk response strategies for the project definition update should you use? (Each correct answer presents part of the solution, Choose two.)
-
Exploit
-
Avoid
-
Enhance
-
Transfer
-
share
Answer: B,D
100% Ensurepass Free Download!
–MB5-705 PDF
100% Ensurepass Free Guaranteed!
–MB5-705 Dumps
EnsurePass | ExamCollection | Testking | |
---|---|---|---|
Lowest Price Guarantee | Yes | No | No |
Up-to-Dated | Yes | No | No |
Real Questions | Yes | No | No |
Explanation | Yes | No | No |
PDF VCE | Yes | No | No |
Free VCE Simulator | Yes | No | No |
Instant Download | Yes | No | No |