QUESTION 51
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
A. |
Raise a request for change |
B. |
Raise an off-specification |
C. |
Write an Exception Report |
D. |
Amend the Work Package |
Correct Answer: B
QUESTION 52
Which is a purpose of the Controlling a Stage process?
A. |
Assign work to be done and take corrective action to ensure that the stage remains within tolerance |
B. |
Provide a fixed reference point at which acceptance for the project product is confirmed |
C. |
Enable the Project Board to be provided with sufficient information to authorize the next stage |
D. |
Enable the organization to understand the work that needs to be done to deliver the project’s products |
Correct Answer: A
QUESTION 53
Which is a purpose of the Managing Product Delivery process?
A. |
Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package |
B. |
Provide a controlled link between the Project Manager and the Team Manager(s) |
C. |
Enable the Project Board to request updates to the current Team Plan |
D. |
Establish solid foundations for the project |
Correct Answer: B
QUESTION 54
What is the collective name for individuals or groups who may be affected by a project?
A. |
Customers |
B. |
Project Support |
C. |
Stakeholders |
D. |
Team members |
Correct Answer: C
QUESTION 55
Which does the Executive need to ensure is in place before the project is initiated?
A. |
All Work Packages are authorized |
B. |
An understanding of how the project will contribute to corporate objectives |
C. |
The Project Plan has been approved |
D. |
The Project Initiation Documentation is complete |
Correct Answer: B
QUESTION 56
Which project management team member represents the interest of those who will operate the project’s products to realize the benefits after the project is complete?
A. |
Executive |
B. |
Senior User |
C. |
Senior Supplier |
D. |
Project Manager |
Correct Answer: B
QUESTION 57
What needs to be in place to ensure effective issue and change control?
A. |
Configuration management system |
B. |
Manage by exception |
C. |
Quality planning |
D. |
Information needs for stakeholders |
Correct Answer: A
QUESTION 58
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
A. |
Checkpoint Report |
B. |
Highlight Report |
C. |
Issue Report |
D. |
Product Status Account |
Correct Answer: C
QUESTION 59
Which of the following statements about stakeholders are true?
1. Someone who thinks they will be affected by a project is a stakeholder on that project.
2. Stakeholders may be internal or external to the corporate organization.
A. |
Only 1 is true |
B. |
Only 2 is true |
C. |
Both 1 and 2 are true |
D. |
Neither 1 or 2 are true |
Correct Answer: C
QUESTION 60
Which is a purpose of the Controlling a Stage process?
A. |
Produce a Team Plan for the work to be assigned to a Team Manager |
B. |
Select and implement actions that will resolve deviations from a plan within tolerance |
C. |
Obtain approvals for products delivered in a Work Package |
D. |
Update a Project Plan to incorporate the actuals from a Stage Plan |
Correct Answer: B
Free VCE & PDF File for PRINCE2 PRINCE2 Real Exam
Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …
100-105 Dumps VCE PDF
200-105 Dumps VCE PDF
300-101 Dumps VCE PDF
300-115 Dumps VCE PDF
300-135 Dumps VCE PDF
300-320 Dumps VCE PDF
400-101 Dumps VCE PDF
640-911 Dumps VCE PDF
640-916 Dumps VCE PDF
70-410 Dumps VCE PDF
70-411 Dumps VCE PDF
70-412 Dumps VCE PDF
70-413 Dumps VCE PDF
70-414 Dumps VCE PDF
70-417 Dumps VCE PDF
70-461 Dumps VCE PDF
70-462 Dumps VCE PDF
70-463 Dumps VCE PDF
70-464 Dumps VCE PDF
70-465 Dumps VCE PDF
70-480 Dumps VCE PDF
70-483 Dumps VCE PDF
70-486 Dumps VCE PDF
70-487 Dumps VCE PDF
220-901 Dumps VCE PDF
220-902 Dumps VCE PDF
N10-006 Dumps VCE PDF
SY0-401 Dumps VCE PDF