QUESTION 31

Which two steps are required to profile an application? (Choose two.)

 

A.      Create a PROFILE package.

B.      Store the package on a file share.

C.      Create an unattended .MSI package.

D.      Store the package on each XenApp server.

 

Correct Answer: AB

 

 

QUESTION 32

After the CRM application has been streamed on the XenApp servers, users complain that they can no longer open contracts for customers stored in the Adobe Acrobat file format through the CRM application. Adobe Acrobat has also been streamed to the XenApp servers. How should the administrator solve this issue?

 

A.      Create a new .MSI package for Adobe Acrobat and publish it.

B.      Create a new .PROFILE package for Adobe Acrobat and publish it.

C.      Create an inter-isolation link between the CRM application .PROFILE file and the Adobe Acrobat .PROFILE file with the streaming application profiler.

D.      Select a .PDF file on all XenApp servers, select ‘pen With’ and make sure that Adobe Acrobat has been associated with .PDF files. Select ‘Always use the selected program to open this kind of file’.

 

Correct Answer: C

 

 

QUESTION 33

An administrator has been asked to configure server-side streaming to the XenApp servers. The application package has been published. Which component is required for server side streaming?

 

A.      Online plug-in

B.      Offline plug-in

C.      Load throttling

D.      Client-to-server redirection

 

Correct Answer: B

 

 

 

 

 

QUESTION 34

An administrator has been monitoring activity on the XenApp servers and determined that most users in an environment access published resources Monday through Friday between 7:00 am and 7:00 pm. The administrator would like to consolidate the number of active sessions outside of this time period to five servers. Which component should the administrator configure to complete this task?

 

A.      Load balancing policies

B.      Preferential load balancing

C.      Health Monitoring and Recovery

D.      Power and Capacity Management

 

Correct Answer: D

 

 

QUESTION 35

What is the proper extension for a roaming profile in the template location for Citrix Profile Management?

 

A.      .DAT

B.      .LOG

C.      .MAN

D.      .PROFILE

 

Correct Answer: A

 

 

QUESTION 36

A company has six servers in the farm. The administrator wants to direct all connections by Research and Development (R&D) employees to Server1. If Server1 becomes unavailable, user connections should be directed to any available server in the farm. What must the administrator do to direct these connections to the appropriate servers?

 

A.      Provide Server 1 with a lower priority than the other servers.

B.      Provide Server 1 with a higher priority than the other servers.

C.      Create two worker groups and configure a load balancing policy.

D.      Add the R&D employees to two worker groups and configure a load balancing policy.

 

Correct Answer: C

 

 

 

 

QUESTION 37

There are 20 servers in a farm. A resource-intensive application is published on five of the servers. An administrator needs to create a load evaluator that reports a full load when the number of users connecting to one of the five servers hosting the application exceeds 60. The administrator must also ensure that only users in a particular location can access the five servers hosting the application. Which two load management rules must the administrator configure for the load evaluator? (Choose two.)

 

A.      IP Range

B.      Scheduling

C.      Load Throttling

D.      Server User Load

 

Correct Answer: AD

 

 

QUESTION 38

A company has nine servers in the farm. An administrator wants to set the preference for user connections from Austin to three specific servers. What must the worker group contain to direct Austin user sessions to these servers?

 

A.      The servers in the farm

B.      The Austin user accounts

C.      The three specific servers

D.      The Austin user accounts and servers

 

Correct Answer: C

 

 

QUESTION 39

A farm contains 10 servers. An application is published on two of the servers. An administrator needs to apply a load evaluator that reports a full load when the number of users connecting to the application exceeds 100. Which load evaluator would the administrator use to meet the requirements of the scenario?

 

A.      Default load evaluator assigned to the server

B.      Custom load evaluator assigned to the server

C.      Custom load evaluator assigned to the application

D.      Advanced load evaluator assigned to the application

 

Correct Answer: C

 

 

QUESTION 40

Users are experiencing issues when attempting to connect to publish resources through Access Gateway. Which two should the administrator monitor? (Choose two.)

 

A.      Terminal Services

B.      Citrix XTE Service

C.      Citrix IMA Networking

D.      Secure Ticket Authority

 

Correct Answer: BC

 

 