QUESTION
Which of the following would be included in the project transition plan?
A. Specifications used for quality control measurements.
B. Comparison of project deliverables with organizational strategic goals.
C. Maintenance responsibilities of the project deliverables.
D. Analysis of the project expenditures.

 

Correct Answer: C

 

QUESTION 192
Which of the following would be included in a project scope document? (Select TWO).
A. Project constraints
B. WBS dictionary
C. Project assumptions
D. Project charter
E. Work Breakdown Structure (WBS)
Correct Answer:C

 

QUESTION 193
Which of the following would be the BEST tool to estimate activity time durations?
A. Gantt chart
B. CPM
C. Estimating model
D. PERT

 

Correct Answer: D

 

QUESTION 194
Which of the following is a function of the change control board?
A. Responsible for creating the work packages in the work breakdown structure (WBS).
B. Responsible for reviewing change requests to determine if additional analysis is required.
C. Responsible for updating the project sponsor on all changes that occur during the project.
D. Responsible for making changes to high level projects.

 

Correct Answer: B

 

QUESTION 195
Which of the following is a result of an approved change request?
A. Update the project charter to reflect the approved change request.
B. Update the project plan to reflect the approved change request.
C. Update the issues log for review during project closure.
D. Ensure no further action is required by the change request board.

 

Correct Answer: B

 

QUESTION 196
Which of the following is a FINAL step when closing an approved change request?
A. Notify the executive steering committee of the approved changes.
B. Notify the project sponsor affected by the approved change.
C. Notify the project manager of the approved changes.
D. Notify all members of the project team that the changes have been approved.

 

Correct Answer: D

 

QUESTION 197
Which of the following is an example of withdrawal?
A. Withdrawal is considered an avoidance technique.
B. Withdrawal is a way of confronting a problem to find the best solution.
C. Withdrawal is considered a win-win situation.
D. Withdrawal is considered a win-lose situation.
Correct Answer:

 

QUESTION 198
How is the critical path method (CPM) determined?
A. The longest path in the network diagram and the earliest and latest date an activity can be
started.
B. The longest path in the network diagram and the earliest and latest date an activity can start
and be completed.
C. The shortest path in the network diagram and the earliest and latest date an activity can start
and be completed.
D. The longest path in the network diagram and the earliest and latest date an activity can be
completed.

 

Correct Answer: B

 

QUESTION 199
Under which of the following organization structures do subject matter experts (SMEs) comprise
an independent project team that reports solely to a project manager?
A. Traditional
B. Strong matrix
C. Projectized
D. Weak matrix

 

Correct Answer: C

 

QUESTION 200
A team member reports that another team member is difficult to work with. The project
manager agrees to address these concerns at a later date. This is an example of which of the
following conflict resolution methods?
A. Avoiding
B. Forcing
C. Compromise
D. Smoothing

 

Correct Answer: D