Latest CompTIA PK0-003 Real Exam Download 261-270

 

QUESTION
Which of the following documents would contain the date the ownership of a project閳ユ獨 final
deliverable would be turned over to operations?
A. Transition plan
B. Risk plan
C. Communications plan
D. Quality plan
Correct Answer:

 

QUESTION 262
Which of the following would MOST likely possess the authority to approve a modification to the
project?
A. Change control board
B. Key stakeholder
C. Project manager
D. Functional manager
Correct Answer:

 

QUESTION 263
A quality audit would be performed during which of the following processes?
A. Quality planning
B. Quality assurance
C. Quality control
D. Pareto analysis

 

Correct Answer: B

 

QUESTION 264
Which of the following is a sequential visual representation of a process used to show activities
and decision points?
A. Ishikawa diagram
B. Histogram
C. Flow chart
D. Control chart

 

Correct Answer: C

 

QUESTION 265
A project manager has analyzed work performance information and identified alarming variances
in the project deliverable. Which of the following would be the BEST response for the project
manager?
A. Perform a qualitative risk assessment.
B. Speak with the project sponsor about possible solutions.
C. Approve a change request to correct the actions.
D. Recommend corrective actions.

 

Correct Answer: D

 

QUESTION 266
A project manager is completing a project schedule network diagram using boxes to represent
the project activities that are connected by lines to show their dependencies. Which of the
following tools is the project manager using?
A. AOA
B. WBS
C. ADM
D. PDM

 

Correct Answer: D

 

QUESTION 267
Activity A is the predecessor to activity B. The project manager cannot begin work on activity B
until activity A is completed. This is an example of which of the following dependencies?
A. Start-to-Start
B. Start-to-Finish
C. Finish-to-Start
D. Finish-to-Finish

 

Correct Answer: C

 

QUESTION 268
A key stakeholder is annoyed because they have not been informed of the project status
meetings. Which of the following documents has the stakeholder been overlooking?
A. Work performance report
B. Transition plan
C. Milestone report
D. Communications plan

 

Correct Answer: D

 

QUESTION 269
Why does the project manager determine the risk tolerance for a project?
A. It is used to determine the variance of the project deliverable from the acceptance criteria.
B. It is used to determine which risks should be accepted.
C. It is used to determine the impact of project risks if they occur.
D. It is used to determine the probability of project risks.

 

Correct Answer: B

 

QUESTION 270
A project manager needs to replace someone on the project team. Which of the following is the
FIRST action they should take?
A. Consult the project staffing plan.
B. Notify the human resources department to open a job posting.
C. Search for skilled subcontractors who could quickly fill the opening.
D. Ask the project sponsor for another resource.
Correct Answer: