Ensurepass
Latest CompTIA PK0-003 Real Exam Download 271-280

 

QUESTION
A conflict has developed among two project team members. The project manager reiterates the
areas of agreement and avoids the areas of disagreement. Which of the following BEST describes
this conflict resolution technique?
A. Smoothing
B. Compromising
C. Avoiding
D. Negotiating
Correct Answer:

 

QUESTION 272
A stakeholder informed the project manager of an unauthorized modification to the project
deliverable. It appears that the modification will benefit the project and allow early completion.
Which of the following should the project manager do?
A. The modification should be removed from the project until a change request is approved.
B. The stakeholder should be required to review the remainder of the project to locate
additional improvements.
C. Even though the modification might benefit the project, the stakeholder should be removed
from the remainder of the project and their manager should be notified.
D. The modification should be noted in the change log and the project should be reviewed to
locate any negative impact.

 

Correct Answer: D

 

QUESTION 273
Which of the following is a common project selection method?
A. Work Breakdown Structure (WBS)
B. Benefit measurement
C. User acceptance testing
D. System design specification

 

Correct Answer: B

 

QUESTION 274
During which of the following phases is funding FIRST approved for the project?
A. Planning
B. Execution
C. Monitoring
D. Initiation

 

Correct Answer: D

 

QUESTION 275
Which of the following documents provides formal approval to start the project?
A. Resource assignment matrix
B. Project charter
C. Work Breakdown Structure (WBS)
D. Contract administration

 

Correct Answer: B

 

QUESTION 276
A project scope statement includes which of the following items? (Select THREE).
A. Major deliverables
B. Success criteria
C. Constraints
D. WBS
E. Scope management plan
F. Mandatory dependencies
Correct Answer:BC

 

QUESTION 277
Which of the following directly utilize the WBS? (Select TWO).
A. Communication plan
B. Monte Carlo technique
C. Activity estimation
D. Variance analysis
E. Resource assignment

 

Correct Answer: CE

 

QUESTION 278
Which of the following BEST identifies the correct number of layers in a WBS?
A. WBS should decompose to a manageable level to use the activity.
B. WBS decomposition depends on the complexity of the overall project.
C. WBS should decompose until activities are broken into small, specific tasks.
D. WBS decomposition has the same number of levels for all objectives.
Correct Answer:

 

QUESTION 279
Click on the Exhibit button. Which of the following is the duration of the path: start-A-B-E-C-end?
A. 16
B. 17
C. 18
D. 19

 

Correct Answer: C

 

QUESTION 280
Click on the Exhibit button. Which of the following is the float of the path: start-A-D-end?
A. Zero
B. One
C. Five
D. Nineteen
Correct Answer: