QUESTION
A project manager閳ユ獨 experience shows that when using four laborers they can produce ten
deliverables. Now the project manager uses eight laborers and produces fifteen deliverables.
This is an example of which of the following?
A. Learning curve
B. Law of diminishing return
C. 80/20 rule
D. Parametric cost estimating

 

Correct Answer: B

 

QUESTION 332
The process of decomposing deliverables into smaller components is complete when:
A. manageable cost and duration estimates can be developed
B. project justification has been established
C. change requests have been approved
D. each work element is found in the WBS and the WBS dictionary
Correct Answer:

 

QUESTION 333
A project manager has an initial problem with a remote team member閳ユ獨 performance. Which of
the following is the BEST form of communication to address this issue?
A. Formal written communications
B. Informal written communications
C. Informal verbal communications
D. Formal verbal communications

 

Correct Answer: C

 

QUESTION 334
Which of the following techniques graphically represents schedule activities as nodes and uses
arrows to define the sequence relationship between them?
A. Activity-on-Arrow (AOA)
B. Arrow Diagram Method (ADM)
C. Work Breakdown Structure (WBS)
D. Precedence Diagram Method (PDM)

 

Correct Answer: D

 

QUESTION 335
The testing of a deliverable to determine whether or not it meets previously defined acceptance
criteria is an example of which of the following?
A. Quality assurance
B. Change control
C. Quality control
D. Risk matrix analysis

 

Correct Answer: C

 

QUESTION 336
The design of standards and specifications by which to test the functionality of a deliverable is a
component of which of the following?
A. Scope control
B. Change control
C. Quality assurance
D. Risk matrix analysis

 

Correct Answer: C

 

QUESTION 337
Industry regulations require that an organization keep all project-related documents for no less
than seven years. Which of the following should the project manager implement to BEST address
this requirement?
A. Version control policy
B. Document retention policy
C. Auditing policy
D. Standards compliance

 

Correct Answer: B

 

QUESTION 338
All of the following are included in the project scope document EXCEPT the:
A. project assumptions
B. key performance indicators
C. alignment to strategic goals
D. project charter

 

Correct Answer: D

 

QUESTION 339
All of the following are characteristics of a WBS EXCEPT: (Select TWO).
A. shows a graphical timeline of project activities
B. shows a hierarchal breakdown of project work
C. shows major project milestones
D. used as a tool to make project cost estimates
E. includes a dictionary as a supporting document
Correct Answer:C

 

QUESTION 340
All of the following occur during the project closure phase EXCEPT:
A. ensure the project is aligned with organizational goals
B. ensure document retention compliance is being performed
C. release project team resources
D. close contracts and pay vendors
Correct Answer: