Ensurepass
Latest CompTIA PK0-003 Real Exam Download 341-350

 

QUESTION
Which of the following would be used to ensure quality of project deliverables?
A. RFP
B. Earned value analysis
C. Schedule compression
D. WBS

 

Correct Answer: D

 

QUESTION 342
Which of the following is the MOST appropriate definition for quality assurance?
A. Quality assurance is the monitoring and analysis of a specific project and test results to
evaluate whether the project and its outputs comply with relevant quality standards.
B. Quality assurance is the process of identifying appropriate quality standards that are
pertinent to the project and determining how to complete them.
C. Quality assurance is the application of planned and systematic quality actions necessary to
provide confidence that the project is deploying all the correct processes required to meet
the project objectives.
D. Quality assurance is the identification, via provided statistical information, of ways to
eliminate causes of unsatisfactory performance, or defects within product architecture.

 

Correct Answer: C

 

QUESTION 343
Which of the following is the MOST appropriate definition for quality control?
A. Quality control is the monitoring and analysis of specific project and test results to evaluate whether the project and its outputs comply with relevant quality standards.
B. Quality control is the process of understanding, analyzing, defining and managing customer expectations so that customer requirements are met.
C. Quality control is the application of planned and systematic quality actions necessary to provide confidence that the project is deploying all the correct processes.
D. Quality control is the process of identifying appropriate quality standards that are pertinent to the project and determining how to satisfy them.
Correct Answer:

 

QUESTION 344
Which of the following is the activity to determine the individuals that will be affected by the
project?
A. Stakeholder identification
B. Project team acquisition
C. Staff management planning
D. Feasibility analysis
Correct Answer:

 

QUESTION 345
A document that formally authorizes a project and empowers the project manager to commence
the organization and deployment of resources is the:
A. staff management plan
B. project plan
C. project scope statement
D. project charter

 

Correct Answer: D

 

QUESTION 346
The key document that is a detailed, hierarchical decomposition of the work to be undertaken to
address the objectives and meet the requirements of the project at the lowest level, is called:
A. RACI
B. RBS
C. SOW
D. WBS

 

Correct Answer: D

 

QUESTION 347
The purpose of a WBS dictionary is to provide:
A. additional details for each component of the WBS, and for each component provide a brief
definition of its statement of work, outputs, actual activities and pertinent milestones
B. a detailed glossary of terms used in the WBS
C. written authorization to sanction work on a particular work-package within the WBS, and
define the methods for its implementation and the monitoring of its performance
D. a hierarchical decomposition of the work to be undertaken to address the objectives and
meet the requirements of the project at the lowest level
Correct Answer:

 

QUESTION 348
Details of eventual ownership, training requirements for end users, extended support and
warranty/maintenance information regarding the project deliverables are included in which of
the following documents?
A. Procurement management plan
B. Transition plan
C. Staff management plan
D. Project scope statement

 

Correct Answer: B

 

QUESTION 349
A customer has stringent requirements on their vendors and service providers to ensure their
environmental compliance. This is a key element of the customer閳ユ獨 marketing to their own
customers. The customer provides a detailed list of requirements regarding the nature and
source of the components that the project will use. The project sponsor agrees to meet the
requirements, which become a subsequent part of the project scope. These requirements are an
example of:
A. standards compliance
B. internal process compliance
C. ISO compliance
D. legislature compliance
Correct Answer:

 

QUESTION 350
Which of the following is MOST likely to approve a project charter?
A. Project manager
B. Business analyst
C. Subject matter expert (SME)
D. Project sponsor

 

Correct Answer: D